How to set up a pump reliability program

Short answer

A pump reliability program is a routine for finding out which pumps fail most, why, and what stops it. It needs three things: an accurate list of the pumps you have, a record of every failure with its cause and cost, and one person responsible for working through the worst machines. In most plants a small share of the pumps accounts for a large share of the repair spend, so the first job is to find them.

What to record for every failure

RecordWhy it mattersWhere it usually comes from
Pump tag and serviceTies the failure to one machine, not to a modelEquipment list
Date, and run time since the last repairGives the time between failuresWork order, hour meter
What failed: seal, bearing, coupling, impeller, motorShows the pattern on that pumpRepair report
Why it failed: the cause, not the partThe only thing that prevents the next oneRoot cause analysis
Parts and labor costRanks pumps by money, not by how often they are mentionedPurchase orders, time sheets
Downtime, and what it costOften larger than the repair itselfOperations

1. List what you have

Walk the plant and record what is actually installed: tag, service, make, model, size, seal, motor. Records drift as pumps are swapped and rebuilt, so do not rely on the old list. Then rate each pump by what happens when it stops: a safety or environmental risk, lost production, or nothing because the spare takes over. That rating decides where the effort goes.

2. Record every failure and what it cost

Agree what counts as a failure and keep to it. A common definition is any event that takes the pump out of service for repair. Record each one against the pump's tag, using the table above. Cost matters as much as count: a pump that fails twice a year at high cost deserves attention before one that fails four times for the price of a seal.

3. Measure and rank

Calculate mean time between failures for the plant and for each pump; the guide to calculating pump MTBF has the formula and a worked example. Then sort the list by number of failures and by cost. The pumps at the top are the bad actors, and the list is usually short.

4. Find the cause of each repeat failure

A bad actor gets a root cause analysis, not another repair. Keep the failed parts, read them, and check how the pump was running. The same causes come up from plant to plant:

5. Fix the cause and write down the standard

Make the change the analysis points to: trim the impeller or change the control so the pump runs near its best efficiency point, correct the seal flush, fit bearing protection, regrout the base. Then make it the standard, so the next repair does not undo it: alignment tolerances, how seals are installed, which lubricant goes where. A repair shop that reports the cause with every repair makes this much easier.

6. Watch condition between failures

Once the worst pumps are dealt with, monitoring catches the next problem early.

  • Vibration readings on a route, or continuous monitoring on critical machines
  • Motor power monitoring, which shows dry running and off-design operation. See power monitors.
  • Oil analysis and a planned lubrication program. See lubrication audits and training.
  • Operator rounds: leaks, noise, temperature, oil level

7. Review the numbers on a schedule

Look at MTBF, cost per pump and the bad actor list at a fixed interval, monthly or quarterly. Close out each root cause action and check that the pump has stopped failing. A program that is not reviewed turns back into a repair log.

Who should run it

One named person, with time set aside for it. In a small plant that is the maintenance or reliability lead. Plants without that person can contract it: Southern Design's Reliability Management System builds the equipment database, reports MTBF and cost per machine, and assigns a lead reliability engineer to work through the bad actors with you.

Frequently asked questions

What is a pump reliability program?

A routine for recording pump failures, finding their causes and fixing those causes, so the same pumps stop failing. It combines an equipment list, failure and cost records, root cause analysis and condition monitoring.

What is a bad actor?

A pump that fails far more often, or costs far more to keep running, than the rest. Bad actors are where a reliability program starts.

Do we need software to start?

No. A spreadsheet with one row per failure is enough to start. Software earns its place when there are too many pumps and repairs for one person to keep straight.

How long before a reliability program shows results?

The bad actor list is usually clear once a year of failure records is in one place. Results follow as each cause is fixed, so the timing depends on how quickly the changes are made.

Products and services that help

Written by the Southern Design reliability team. Last reviewed October 2026.